26-21 Water Street Sewer Improvements Phase B - Hopkins Alley to Front Street
Description: The City of Ketchikan seeks qualified contractors for Phase B of the Water Street Sewer Improvements from Hopkins Alley to Front Street. Work includes replacing or rehabilitating sewer pipelines, street demolition and excavation with surface restoration, and coordination with Ketchikan Public Utilities for water-line protection and traffic management. The work must comply with applicable environmental requirements, and bids close on November 20, 2026.
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
Construct the proposed water, street & drainage improvements. Construction consists of approx. 3,600 LF of twenty-foot-wide urban roadway including curb and gutter, storm drainage pipe and boxes, base and asphalt, approx. 1,230 LF of 2" PVC water main replacement with the transfer of existing water services, fire hydrants, etc., and all associated measures for the complete project.
The Town of Robbinsville seeks construction bids for Laura Street Sewer System Improvements under CDBG-I Project 21-I-4002. Work includes approximately 2,100 linear feet of 8-inch ductile iron gravity sewer and 830 linear feet of 12-inch ductile iron gravity sewer in the Laura Street/US129 area. The contractor will also reconnect existing sewer services and install related accessories and appurtenances.
The Town of Robbinsville seeks construction bids for Laura Street Sewer System Improvements under CDBG-I Project 21-I-4002. Work includes approximately 2,100 linear feet of 8-inch ductile iron gravity sewer and 830 linear feet of 12-inch ductile iron gravity sewer in the Laura Street/US129 area. The contractor will also reconnect existing sewer services and install related accessories and appurtenances.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
341 days before RFP
Staff projected a further 6.0% wastewater rate increase in FY27 to fund debt service for the ADEC-loan-funded Water Street Sewer Main Replacement, Phase II project.
See sourceHide source
o Wastewater (Budget Page 75) Wastewater rates are programmed for an 8.0% increase for FY26 to meet capital needs and a collective bargaining agreement-related increase. Use of fund balance reserves is programmed for the 14% difference between revenue and expenditures for a $1,526,005 deficit. FY27 will require a 6.0% above the current rate increase…
The City of Ketchikan Wastewater Services CIP proposed phased Water Street sewer replacement and rehabilitation, including Phase B, with $4.3 million budgeted for FY2026 and $2.5 million for FY2027.
See 3 sourcesHide sources
Water Street Sewer Replacement & Rehabilitation Overview Department Wastewater Services Type Capital Improvement Project Number 3000-02 Estimated Start Date 01/1/2026 Estimated Completion Date 12/31/2030 Description The south end of Water Street is located between Kennedy Street and Front Street. The manholes in this section of gravity sewer are known to be…
City of Ketchikan Capital Improvement Program 2026-2030
Board meeting
289 days before RFP
The City Council approved submitting a $2,800,000 loan-amendment application, for a total $6,700,000 loan, for the Water Street Sewer Replacement & Rehabilitation project.
See sourceHide source
Resolution No. 26-3004, Authorizing the Submittal of a $2,800,000 Loan Amendment Application for Loan No. 481211- S to the State of Alaska Department of Environmental Conservation for Funding Through the Alaska Clean Water Fund, for a Total Loan Amount of $6,700,000 for the Water Street Sewer Replacement & Rehabilitation Project Moved by Gage, seconded by…
Ketchikan City Council Regular Meeting
Board meeting
135 days before RFP
The City Council approved on second reading an ordinance authorizing up to $15,000,000 in sewer-fund obligations for wastewater-system improvements.
See 2 sourcesHide sources
Ordinance No. 26-2030, Amending Ordinance No. 18-1867 Which Authorizes Junior Lien Obligations Payable from the City's Sewer Fund in the Principal Amount Not to Exceed $15,000,000 to Finance Costs of Wastewater System Facilities -- Second Reading Copies of Ordinance No. 26-2030 were available for all present. Moved by Finnegan, seconded by Mahtani the City…
Moved by Finnegan, seconded by Gage the City Council approve Ordinance No. 26-2030, in first reading, amending Ordinance 18-1867, which authorizes junior lien obligations payable from the City's sewer fund in the principal amount of not to exceed $15,000,000 to finance costs of improvements to Wastewater System Facilities; and establishing an effective…