26-182-CIP - Pipeline Relocations and Repairs at FM 1641, FM 987 and Cathodic Protection Relocations at FM 741
The North Texas Municipal Water District (NTMWD) is soliciting bids under ITB 26-182-CIP to replace nine segments of its existing 20-inch water pipeline totaling approximately 324 linear feet, relocate an additional 16,700 linear feet of 20-inch pipeline, and replace an existing meter vault. The work also includes relocating two cathodic test stations to the existing 108-inch tunnel liner plate at two crossings of the 84-inch NTMWD pipeline where TxDOT’s right-of-way is expanding. The official Bonfire posting is an open procurement (not a grant), lists an OPCC of $18M - $23M, and shows an open date of Aug 13th 2026, 9:00 AM CDT and a close date of Sep 17th 2026, 2:00 PM CDT.