Provide wastewater collection system rehabilitation.
Description: Work includes erosion control; mainline video inspection; 113 internal service reinstatement; 4,028.7 LF of 8" CIPP liner.
City · OR, US
From the first pre-RFP signals to the published RFP and its files.
Strategic plan
The Consolidated Plan identifies needs for pipe replacements, system expansions, and improved drainage solutions.
Medford also faces challenges with water and sewer capacity, particularly in newly developed areas. The 2019 Sewer Master Plan and ongoing stormwater management updates have identified areas requiring pipe replacements, system expansions, and improved drainage solutions. The city's Public Works Department is working closely with the Medford Water Commission…
City of Medford Consolidated Plan 2025-2029
Strategic plan · 2025
Repairs and improvements to public infrastructure, including streets, sidewalks, lighting, alleyways, sewers, and curbs and gutters in low-income areas.
City of Medford Consolidated Plan 2025-2029
Strategic plan · 2025
One key strategy is expanding infrastructure investments. The City is implementing its Sewer Master Plan and working with the Medford Water Commission to improve infrastructure City of Medford 2025-2029 Consolidated Plan 177 planning. These efforts aim to reduce development costs and make new housing projects
City of Medford Consolidated Plan 2025-2029
Strategic plan · 2025
Strategic plan
494 days before RFP
The Council Goal Action Items document directs completion of Public Works capital projects for sewer capacity and stormdrain work.
Continue to support and modernize infrastructure throughout the City. 1. Complete Capital Improvement Projects included in the Public Works 2025- 2027 Biennial Budget (Sewer Capacity, Stormdrain, Foothill Rd., Safe Routes to School, etc.).
City Council Goal Action Items
Strategic plan · Jun 27, 2025
Annual financial report
491 days before RFP
The budget lists storm drain system development and capital outlay for the biennium.
City of Medford Schedule of Revenues, Expenditures, and Changes in Fund Balance - Budget and Actual (Budgetary Basis) Storm Drain Utility Fund - 501 For the Year Ended June 30, 2025 First Year Second Year Variance With Original Final Actual Actual Total Actual Final Budget REVENUES Charges for services 13,140,800$ 13,140,800$ 6,555,692$ 6,820,334$…
City of Medford, Oregon Annual Comprehensive Financial Report FY2025
Annual financial report · Jun 30, 2025
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (12 days left)
Decision makers connected to this RFP from City of Medford.
Adjacent opportunities open for bidding right now.
CityLA
Posted
Oct 29, 2026
Dec 1, 2026
Provide wastewater collection system rehabilitation.
CityAL
Posted
Nov 4, 2026
Nov 20, 2026
Work inlcudes 200 LF new city std. (24") concrete curb and gutter; 100 LF new (24") concrete valley curb ; 200 SY 4" thick concrete for new sidewalk and/or traffic islands ( less than 200 SY); 200 SY 6" thick concrete for new sidewalk and/or traffic islands and/or driveways; 80 SY new 6" thick concrete driveway aprons; 80 SY new 4" thick concrete driveway with 6x6w 2.9 reinforcing wire mesh; 500 LF removal of concrete curb and gutter or valley gutter (includes disposal of spoils). See attached file.
CityTX
Posted
Oct 25, 2026
Nov 19, 2026
Seeking qualified vendors for wastewater treatment plant phase 2 - collection system rehabilitation.
CityLA
Posted
Oct 29, 2026
Dec 1, 2026
Provide wastewater treatment and collection system rehabilitation.