Open RFP

1412223678 (RFP) Circuit 680 UG Cable Replacement Construction Services

Description: JEA seeks a contractor to replace approximately 1,200 feet of 69 kV underground cable originating at the Dillion Substation, with work spanning the substation and generation facility and nearby Jacksonville rights-of-way. The project includes new concrete-encased and HDD duct banks, installation of 69 kV EPR cable, modifications to transmission and substation structures, removal of existing cable, site restoration, traffic maintenance, and permitting. Responses are due October 27, 2026, following a mandatory pre-response meeting scheduled for October 5, 2026.

Buyer
JEA

SpecialDistrict · FL, US

Released
-
Closes
Oct 27, 2026(27 days left)