Schedule I: Runway Extension, Schedule II: West Partial Parallel Taxiway and Apron, Schedule III: East Partial Parallel Taxiway
Posted
Oct 4, 2026
Nov 10, 2026
Schedule I: Runway Extension, Schedule II: West Partial Parallel Taxiway and Apron, Schedule III: East Partial Parallel Taxiway. Items of work include erosion control installation, earthwork, storm drainage installation, aggregate base course placement, asphalt paving (P-401 and P-404), shoulder grading, marking, lighting and signage, PAPI installation, vault installation, seeding, sodding, and mulching.