Kramer Road Reconstruction
Jul 27, 2026
Closes
Aug 11, 2026
Project includes Contract Alternative No. 1: Kramer Road Stormwater Improvements – Saw cutting and removal of approximately 280 sq. yd. of asphalt pavement, fine grading, asphalt patch paving (3.5” Thickness), approx. 480 LF of asphalt screed curb, 300 LF of 12” SDR-35 Storm Sewer pipe, four 2x3 catch basins with inlet grates & castings, topsoiled & grassed shoulder restoration, erosion control, and traffic control. Contract Alternative No. 2: Kramer Road Reconstruction – Pulverizing of approximately 1,200 sq. yd. of asphalt pavement, fine grading, asphalt paving (3.5” Thickness, 10’ lanes), approximately 480 Lin. Ft. of asphalt screed curb, 300 LF. of 12” SDR-35 Storm Sewer pipe, four 2x3 catch basins with inlet grates & castings, topsoiled & grassed shoulder restoration, erosion control, and traffic control.