Chestnut Street Lift Station Replacement RFP
Jul 28, 2026
Closes
Aug 18, 2026
The Village of Park Forest, Illinois is soliciting sealed bids for the construction of the Chestnut Street Lift Station Replacement, with proposals due August 18, 2026 at 2:00 PM at the Village Hall, 350 Victory Drive, Park Forest, IL 60466. The work includes rehabilitating the existing wet well, installing a valve vault, control panel, two 5 hp submersible pumps, 696 feet of 4-inch force main, 48 feet of storm sewer, abandonment and removal of existing facilities, surface restoration, and other miscellaneous items. Bidding documents may be examined at the Village Hall or obtained from BHFX Digital Imaging at www.bhfxplanroom.com for $90 per printed set or $45 per digital download, and all bids must be accompanied by a bidder's bond or certified check equal to 10% of the bid amount.