Date of Issue: November 9, 2026
Proposals Due: December 15, 2026
At or Before 3:00 P.M. Local Time
Section 1 - Intent of the Request for Proposal
1.1 BACKGROUND INFORMATION
The City of Lemoore ("City") is soliciting proposals from qualified consulting firms ("Consultant") for an Installation Readiness Review. The Office of Local Defense Community Cooperation (OLDCC) has offered the City grant funds to conduct a Military Installation Readiness Review of Naval Air Station (NAS) Lemoore to inform the development of risk-based strategies and action plans, which may lead to further analysis and design of solutions for shared infrastructure. Community partners and companies provide critical utility connections to support the base, its mission, and its personnel, the majority of whom live in the surrounding communities. The grant is federally funded by the Department of Defense through the OLDCC Installation Readiness Program. This project will be a collaborative effort with the City, OLDCC, and NAS Lemoore. The OLDCC operates under the Department of Defense and serves as the primary federal resource for local community coordination. This project will foster a collaborative resiliency effort in the Lemoore area and surrounding community to build local capacity, develop cross-sector partnerships, and support military readiness and community resiliency. The resulting action plan from this readiness review will guide investments in infrastructure and services to enhance the military mission, achieve savings in facilities and infrastructure, and increase military and civilian readiness and resilience across the region.
The Consultant providing a proposal in response to this RFP must address every item in the Description of Services to be Performed, as set forth in Section 2. In addition, proposals must be in the format set forth in Section 3.2 of this RFP. Failure to include all elements in Section 2 or submit a proposal in the required format may be grounds for rejection of the proposal. In the event the Consultant wishes to take an exception to any of the requirements set forth in Section 2, those exceptions must be clearly stated in the proposal. Failure to include any item in the specifications without taking exception will result in a waiver of the Proposer's ability to negotiate a contract term, attempt to request additional compensation for elements in Section 2 that were not included in the pricing set forth in the proposal, and may be grounds for rejection. The City reserves the right to reject all proposals and/or to waive any informality in the accepted bid. The City reserves the right to reject all bids with or without cause and re-issue this RFP if deemed to be in the City's best interests.
1.2 LOCATION WHERE SERVICES ARE TO BE PERFORMED
The Consultant shall provide their own office/workspace but be available to travel to all parts of the project area as needed to complete the scope of work.
1.3 PRICE
The Consultant must include all information on pricing in their proposals. Although the City will base its selection on all factors, pricing information is required to confirm the City receives the requested services or work at a fair and reasonable price. Failure to include pricing information in a proposal may result in a rejection of the proposal as non-responsive. Consultant shall include in their hourly rate the cost of travel, supplies, and other costs associated with tasks, in their proposed hourly rate estimate.
1.4 PROPOSED TERM
The project is expected to be completed by June 30, 2027. The City anticipates a 6-month agreement with an optional 6 month extension (the extension to be contingent on approval from the funding agency) between the City and the successful Consultant, but the successful Consultant may design a timeline suitable for completion of the scope of work provided in Section 2. Services shall begin upon contract execution.
1.5 Q&A SESSION
The City will hold a virtual Q&A session via Microsoft Teams on November 30, 2026, to answer questions regarding this Request for Proposals and the scope of work included in Section 2. This is a non-mandatory Q&A. The session will be held on November 30, 2026, 11:00 am - 12:00 pm (local time).
1.6 ELIGIBLE PROPOSERS
Public or private corporations, agencies, organizations, associations, or individuals are invited to submit a proposal in response to this solicitation. The proposer must include their Unique Entity Identifier (UEI) assigned by the U.S. federal government through SAM.org to identify businesses, nonprofits, and organizations doing business or receiving federal funding. The Proposer must not be listed on either list of the 500 largest tax delinquencies pursuant to the Taxation Code Sections 7063 or 19195. Proposers should have an established reputation and documented successful experience in providing military-related planning and engineering services. The selected Proposer is expected to have appropriately experienced staff and resources to provide comprehensive and reliable services for the project and will be required to demonstrate this through the submittal documents and/or associated interviews, if deemed necessary.
1.7 GENERAL PREPARATION AND SUBMITTAL REQUIREMENTS
One clearly marked original and five additional hard copies of the proposal, and one digital copy (flash drive), shall be enclosed in a sealed envelope or carton clearly marked "Readiness Review Project RFP Response" and delivered in person, by carrier, or messenger, by U.S. Mail certified, to the attention of: City of Lemoore, City Clerk, 711 W. Cinnamon Drive, Lemoore, CA 93245. Proposals must be delivered no later than: December 15, at 3:00 PM. Late proposals will not be considered. Any inquiries for additional information, clarifications, discrepancies, or inconsistencies in the instructions or proposal requirements will only be accepted in writing to CITYCLERK@LEMOORE.COM with Readiness Review RFP in the subject line, until December 2 at 3:00 PM.
Section 2 - Description of Services to be Provided
2.1 PROJECT SUMMARY
This project supports resilience and mission assurance for NAS Lemoore by assessing shared vulnerabilities and risks across critical infrastructure sectors (water, electrical, wastewater, communications) and developing readiness action plans, prioritized projects, and recommended funding sources. Two consultants will work on the project: the City of Lemoore's contracted City Engineer (QK) (responsible for water and wastewater) and the successful proposer of this RFP (responsible for coordinating and completing all Tasks associated with everything within this RFP, including electrical and communications analyses, and for incorporating the work and product completed by QK into the final Installation Readiness Review Study).
2.2 TASKS
Task 1. Administrative Execution and Oversight
- Provide project management, host kick-off meeting, focus groups, quarterly meetings, and final close-out meeting. Provide agendas and materials one week prior to each meeting. Deliverables: kick-off, focus group, quarterly, and closeout meeting notes/materials.
Task 2. Participate in Military Community Engagement Process
2A. Participate in communications with NAS Lemoore: recurring monthly project update meetings, develop initial list of documents needed from installation and local government partners, present draft and final products to NAS Lemoore personnel to verify no Controlled Unclassified Information (CUI)-specific data has been included before release.
2B. Steering Committee Support: form and lead a Steering Committee that meets regularly, develop community and stakeholder engagement materials, facilitate kick-off Steering Committee meeting, develop scenarios and participation in tabletop exercises, provide agendas and minutes.
Task 3. NAS Lemoore Military Installation Readiness Review (MIRR)
The successful proposer will be responsible for electrical and communications systems analysis; the City Engineer will handle water and wastewater. The proposer shall integrate City Engineer analysis into final deliverables.
3A. MIRR Kick-Off Meeting: hold kick-off within three weeks of Notice to Proceed (NTP), prepare materials, and submit meeting notes.
3B. Electrical Infrastructure Analysis: gather and review relevant studies, assess backup power/generator issues, assess grid reliability and off-grid operations, identify/prioritize threats and hazards, and prioritize recommended actions (high/medium/low). Deliverables: Electrical Infrastructure Existing Conditions and Electrical Infrastructure Readiness Action Plan.
3C. Communication Infrastructure Analysis: gather and review relevant studies, assess current conditions and connectivity gaps, identify vulnerabilities and cell coverage gaps, consider potential future data center, and prioritize actions. Deliverables: Communications Infrastructure Existing Conditions Report and Communications Infrastructure Readiness Action Plan.
The successful proposer shall compile the Military Installation Readiness Review (MIRR) integrating City Engineer findings for water and wastewater into one cohesive document.
Task 4. Tabletop Exercises and After-Action Reports
4A. Tabletop Exercises: design and facilitate up to three tabletop exercises (or equivalents), coordinate participants including City leadership and NAS Lemoore, infrastructure owners, and other partners, conduct hotwash/debriefs. The first exercise must be held within the first 6 months of the contract.
4B. After-Action Reports: provide design and execution package for exercises and After-Action Reports documenting objectives, participants, scenarios, lessons learned, and recommended follow-up actions.
Section 3 - PROPOSAL FORMAT / Submission Instructions
Proposals must be received by the City of Lemoore, 711 W. Cinnamon Drive, Lemoore, CA 93245, at or before 3:00 p.m. local time on December 15. All proposals shall be submitted on 8 ½ x 11-inch paper and shall be bound or contained in a binder. An electronic version of the proposal must also be provided on a USB drive. Proposers shall submit one (1) original proposal and five (5) copies. The original proposal shall be marked as "Original" on the first page. All proposals must be submitted under seal in either an envelope or box clearly marked with the Name of Proposer/Consultant, RFP Title (Lemoore Military Installation Readiness Review Project), and Due Date: December 15 @ 3:00PM. Proposals shall be delivered to: City of Lemoore, Attn: City Clerk, 711 W. Cinnamon Drive, Lemoore, CA 93245.
Proposals must include the Signature Page (Exhibit A), Cover Letter, Company Overview, Subconsultant List (Exhibit B) if applicable, Relevant Experience with at least five references (Exhibit C), Support Team, Timeframe for Completion, Assistance from City, Proposed Scope of Work addressing Section 2, Acknowledgment of Addenda, Compliance with procurement standards at 2 CFR Part 200, Conflict of Interest certification, Affidavit of Non-Collusion (Exhibit D), and a separate sealed cost envelope with detailed cost breakdown (Exhibit E). Proposals must include a 120-day price guarantee and may not substitute more than 49% of the work to subconsultants.
Section 4 - Selection Process
Issuance of the RFP: November 9, 2026
Q&A Session: November 30, 2026
Proposer's Questions Due: December 2, 2026
City's Answers Due: December 4, 2026
Proposals Due: December 15, 2026
Interviews: TBD
Notice of Intent to Award Sent: December 28, 2026
City Council contract award: January 5, 2027
Services Begin: February 1, 2027
Selection will be based on evaluation criteria set forth in the RFP including demonstrated ability to work with DoD and installations, threat/hazard assessment experience, community engagement experience, qualifications of key personnel, approach to scope, and capacity to perform. Award will be to the highest-ranking proposer deemed most qualified. Additional federal compliance, audit, records, and flow-down requirements apply as described in Section 3 and Exhibit C.
Section 5 - Notice to Proposers - General Information
The RFP summarizes contractual and federal requirements, confidentiality/public-records obligations under California law, prohibitions on late proposals and email/fax submissions, addenda procedures, protest procedures, and other administrative provisions. A draft form of Agreement for Professional Consultant Services and Exhibits (A–F) are attached to the RFP and describe scope, deliverables, milestones, compensation structure (not-to-exceed task allocations to be negotiated), federal and OLDCC contract provisions, required certifications, and insurance/indemnity and termination provisions. The Award period of performance identified in the draft agreement is February 1, 2026 through July 31, 2027 (as stated in the draft agreement language).
Deliverables summarized include: sector-specific existing-conditions reports and readiness action plans for electrical and communications; integration of City-provided analyses for water and wastewater; tabletop exercise packages and After-Action Reports; an integrated MIRR final report and a 2–6 page public executive summary brochure; and GIS deliverables with metadata and editable files.