CityMN
Posted
Sep 18, 2026
Oct 29, 2026
Litchfield, City of Wastewater Treatment Facility Improvements 0W1.125117 RFP
1.Construction of new influent lift station and new utility water lift station. 2.Construction of new pretreatment building with fine screening, vortex grit removal, flow measurement and sampling. 3.Construction of three new 50-foot primary clarifiers 4.Replacement of aeration piping and diffusers. 5.Construction of new rapid mix and flocculation basins with attached chemical and electrical building and Construction of new digester electrical building. 6. Rehabilitation of existing anaerobic digesters.The work includes installing new heat exchangers, sludge transfer pumps, and a new jet mixing system. 7.Demolition of existing DAF equipment and construction of new SAF system. 8.Rehabilitation and demolition of various structures.