Description: This procurement requests construction and related work to upgrade the discharge piping at the Shingle Springs Lift Station per the project specifications and drawings. The work will follow the District-provided NOTICE, SPECIFICATIONS, and DRAWINGS and must comply with the contract and addenda. A mandatory pre-bid meeting was held and only firms represented at that meeting (as shown on the sign-in sheet included in an addendum) are eligible to submit bids.
SpecialDistrict · CA, US
From the first pre-RFP signals to the published RFP and its files.
Agenda packet
38 days before RFP
The draft CIP proposed Shingle Springs Lift Station piping and isolation-valve upgrades, including abandonment of existing piping and installation of a flow meter, with 2027-2031 construction planned.
CAPITAL IMPROVEMENT PLAN Planned Expenditures: Project Financial Summary: Basis for Priority: This project will replace infrastructure at the end of its useful life, remove assets that are no longer in use, and provide flow monitoring for refined system hydraulic analysis. Wastewater Project Description: The Shingle Springs Lift Station, located adjacent to…
El Dorado Irrigation District Regular Meeting
Agenda packet · Oct 13, 2026
Capital improvement plan
25 days before RFP
EID's approved 2027-2031 Capital Improvement Plan lists $500,000 for 2027 construction of Shingle Springs Lift Station Piping Improvements, with $484,122 of additional wastewater-rate funding identified.
25019_Shingle_Springs_LS_Improvements.xlsx 2027 CAPITAL IMPROVEMENT PLAN Program: Wastewater Project Number: 25019 Project Name: Shingle Springs Lift Station Piping Improvements Project Category: Reliability & Service Level Improvements Priority: 2a PM: TBD Project Description: Basis for Priority: Project Financial Summary: Funded to Date: $ 110,000…
El Dorado Irrigation District Capital Improvement Plan 2027-2031
Capital improvement plan · Oct 26, 2026
RFP published
Proposals due (37 days left)
Adjacent opportunities open for bidding right now.
CountyOH
Posted
Nov 5, 2026
Dec 10, 2026
ACTION: Adopted the 2027-2031 Capital Improvement Plan, subject to available funding. MOTION PASSED Ayes: Directors Day, Dwyer, Mansfield, and President Anzini
El Dorado Irrigation District Regular Meeting
Board meeting · Oct 26, 2026
Construction of a new sanitary sewer lift station, including bar screen, wet well, and valve vault structures, submersible pumps, piping, standby power, and electrical & controls improvements, to replace the existing Orchard Valley Lift Station located at 1551 Orchard Valley Drive, Milford Ohio 45150 in Miami Township.
CountyOH
Posted
-
Dec 10, 2026
Construction of a new sanitary sewer lift station to replace the existing Orchard Valley Lift Station at 1551 Orchard Valley Drive, Milford, Ohio, including bar screen, wet well, valve vault structures, submersible pumps, piping, standby power, and electrical and controls improvements. The project includes demolition/replace work and related site and utilities work with all work to be completed within 330 calendar days from the Notice to Proceed. The Engineer's Estimate for the project is $1,572,940.00 and award will be made to the lowest and best bidder subject to applicable funding agency approval and county requirements.
CityNL
Posted
Nov 12, 2026
Dec 3, 2026
The Town of Paradise is seeking a qualified consultant to complete a feasibility study for Woodstock Lift Station Upgrades.
CityLA
Posted
-
Dec 1, 2026
Upgrade of the existing sewer lift stations. These upgrades include demolition of both wet well tops on the existing lift stations, removal of pumps, controls, and discharge piping, and the construction of new wet well rcp extensions, reinforced concrete tops, valve boxes, discharge piping, pumps, control panels, radio communication, new electrical service, sewer manhole rehab, and site improvements as appropriate for complete and operational systems.
Decision makers connected to this RFP from El Dorado Irrigation District.