Design-Build Services for West Hempstead & Winfield Substation Replacements
DESIGN BUILD: West hempstead & winfield substation replacements
Description: DESIGN-BUILD: Design-Build Services for Relocation of the 13kV Substation.
StateAgency · NY, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
668 days before RFP
MTA Bridges and Tunnels proposed a $3 billion 2025–2029 capital plan including renewal and possible flood-elevation of nine substations.
pleased to present you the 2025 29 B&T Capital plan as a national leader in transportation MTA Bridges and tunnels drives the New York City City metropolitan region innovatively managing facilities and delivering significant financial support for the MTA Subways commuter railroads and buses this plan continues critical Investments aimed at extending the…
MTA Board - Bridges and Tunnels Committee Meeting
Board meeting · Sep 23, 2024
Proposed budget
22 days before RFP
MTA Bridges and Tunnels' preliminary budget lists the D904RK9S replacement/relocation of the 13kV substation with a $99.1 million 2026 commitment.
MTA Bridges and Tunnels 2026 Commitments $ in millions ACEP Project Description 2026 Commitments Goal D803AW80 Adv. Traveler Info. Systems (ATIS) & VMS Upgr Element Total $ 23.7 D901CB9Y Security Towers at the CBB Element Total $ 11.0 D901HC9C GIVB FENDER/PEDESTRIAN FOOTBRIDGE REHAB Element Total $ 8.5 D901MP9Y Security Towers at the MPB Element Total $…
Metropolitan Transportation Authority FY2027 Proposed Budget
Proposed budget · Jul 1, 2026
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (2 days left)
Decision makers connected to this RFP from New York Metropolitan Transportation Authority.
Adjacent opportunities open for bidding right now.
Special DistrictNY
Posted
Jun 12, 2026
Nov 17, 2026
DESIGN BUILD: West hempstead & winfield substation replacements
New York Metropolitan Transportation Authority
State AgencyNY
Posted
Sep 18, 2026
Nov 17, 2026
This RFP is for Design-Build Services for West Hempstead & Winfield Substation Replacements.
CityNM
Posted
Jul 22, 2026
Nov 6, 2026
Design-Build services for new carbon coal electrical substation.
Missouri Department of Transportation
State AgencyMO
Posted
Jul 6, 2026
Oct 30, 2026
The Missouri Department of Transportation (MoDOT) is seeking design-build teams for the 291 River Bridge Design-Build Project in Jackson County, Missouri. The project involves replacement of the northbound Missouri Route 291 bridge over the Missouri River (Liberty Bend Bridge, in service since 1949) and rehabilitation of the southbound bridge, with a program budget of $80M and construction completion targeted by December 2029. Following an RFQ phase that pre-qualified five teams on June 18, 2026, MoDOT will issue the Request for Proposals on July 6, 2026, with proposals due October 30, 2026, and best-value proposer selection by the Missouri Highways and Transportation Commission on December 2, 2026.