CityMO
Posted
Nov 6, 2026
Dec 1, 2026
Meadows Water Treatment Facility And Intake Station Emergency Backup Generators RFP
Provide emergency backup generators.
Description: Provide emergency backup generators.
City · MO, US
Adjacent opportunities open for bidding right now.
CityMO
Posted
Nov 6, 2026
Dec 1, 2026
Provide emergency backup generators.
Kansas Department of Health and Environment
State AgencyKS
Posted
Nov 13, 2026
Dec 17, 2026
The City of Bentley is soliciting sealed bids to construct a new wastewater lagoon cell, including excavation, fill, HDPE liner installation and repairs, and riprap placement. Additional work includes force-main and transfer piping, intake and discharge structures, fencing, seeding, and related appurtenances. The construction will be procured under a single prime contract using lump-sum and unit-price bids, with funding provided in whole or in part through the KDHE State Revolving Loan Fund program.
CityIA
Posted
-
Dec 17, 2026
New headworks building (pre-cast concrete) with mechanically cleaned stair screen, screenings washing and compactor, stacked tray grit removal, grit washing, and submersible raw wastewater influent pumps new 4 cell sequencing batch reactor (SBR) treatment process new post treatment building (pre-cast concrete) with tertiary filters (pile cloth) and UV disinfection new biosolids complex building (pre-cast concrete) with rotary drum thickener and sludge pumping new 0.75 MG sludge storage tank (pre-stressed concrete) new operations building (pre-engineered metal building) with blowers (rotary screw), air compressors, compressed air storage tanks, electrical room, mechanical room, lab and control room, and locker room facilities new maintenance building (Bid Alternate A), a pre-engineered metal building demolition of existing plant facilities and structures site grading, paving, structure excavation, underground utilities, and other site civil works electrical work including a new stand-by generator, power and controls, and new SCADA system HVAC and plumbing work for all new buildings all other work as required by the plans and specifications.
CityMN
Posted
-
Dec 17, 2026
Wastewater treatment facility improvements, consisting of preliminary treatment expansion, oxidation ditch improvements, new bioreactor, final clarifier improvements, UV disinfection, sludge storage tank expansion and improvements, administration building improvements and site improvements.
Decision makers connected to this RFP from City of Branson.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
409 days before RFP
Utilities staff proposed, and the Board of Aldermen authorized, seeking county sewer-sales-tax funding for replacement of three Compton Drive wastewater-treatment-facility emergency generators, estimated at roughly $1.7 million.
>> honor, the next item is a resolution authorizing the submitt of applications to Taten County, Missouri for sewer sales tax funding in support of the city's planned 2026 sewer system improvements. >> Do I have a motion adopting this resolution? Second >> motion and a second and we'll have a staff report from Kendall. >> Good evening. Uh the Teny County…
Board Of Aldermen Regular Meeting
Board meeting · Sep 23, 2025
Board meeting
25 days before RFP
Utilities reported that water and wastewater plant emergency generators were in design and currently in progress.
then water and wastewater plant emergency generators um in design. Those that's currently in progress. Uh lift
Board of Aldermen Budget Workshop
Board meeting · Oct 12, 2026
RFP published