HOTEL ROAD BRIDGE REPLACEMENT RFP
Construction of the Hotel Road Bridge over Carey Branch in Bishopville, Maryland.
Description: Installation, maintenance, and removal of traffic protection devices associated with consecutive road closures and detour proposed for this project; Installation, maintenance, and removal of soil erosion sediment control measures at each site; Coordination with utilities for relocation of utility poles at each site; Demolition and replacement of County Bridge No. G1405 with precast concrete rigid frame, precast concrete wingwall at northeast quadrant and cast-in-place wingwalls at other three quadrants, on cast-in-place footings, while keeping Bridge No. G1404 open to local traffic; Demolition and replacement of County Bridge No. G1404 with precast concrete rigid frame and cast-in-place wingwalls, on cast-in-place footings, while keeping Bridge No. G1405 open to local traffic; Approach roadway reconstruction and installation of new beam guide rail and guide rail end terminals, at each site.
County · NJ, US
Solicitation files and supporting documents for this bid.
Decision makers connected to this RFP from Somerset County.
Adjacent opportunities open for bidding right now.
CountyMD
Posted
-
Dec 15, 2026
Construction of the Hotel Road Bridge over Carey Branch in Bishopville, Maryland.
CityCT
Posted
Oct 30, 2026
Dec 10, 2026
Work include 260 LF remove and reset wood fence; 676 CY earth excavation; 34 CY rock excavation; 74 CY excavation and reuse of existing channel bottom material; 38 LF cut concrete sidewalk; 1,200 LF cut bituminous concrete pavement; 1,235 CY structure excavation earth (excluding cofferdam and dewatering); 900 LF cofferdam and dewatering; 50 LF cofferdam material left in place; 164 CY ditch excavation; 1,173 SY formation of subgrade.
CountyID
Posted
Oct 19, 2026
Nov 19, 2026
Replace bridge where Cocolalla Loop Road crosses Cocolalla Creek including roadway approaches, utility coordination, erosion control, traffic control, riprap armoring, and dewatering.
Special DistrictMA
Posted
Nov 12, 2026
Dec 17, 2026
The Sleepy Hollow Road Bridge Replacement Project is located on a rural road in the Town of Richmond located approximately .4 miles east from the intersection of ST 41 and Sleepy Hollow Road. See Location Map below. The bridge crosses Cone Brook, a designated Cold-Water Fishery to the south of the crossing; therefore, construction must protect the stream and restore it to its natural state. Work shall be done, according to the Order of Conditions, Ma Division of Fish & Wildlife NHESP and the Army Corp of Engineers General Permit. The project will require wildlife specialist as part of the turtle protection plan and requirements with the Richmond’s Conservation Order of Conditions. The existing culvert is considered too small to convey high stream flows which has caused significant road overtopping and erosion. The proposed replacement project will replace the culvert with a precast concrete frame structure with precast concrete wingwalls and restore the stream channel to its natural state. The Town will keep the gravel road and not pave it.