New Mexico General Services Department
State AgencyNM
Posted
Oct 22, 2026
Nov 24, 2026
Ready Mixed Portland Cement Concrete D-2
Ready Mixed Portland Cement Concrete for the New Mexico Department of Transportation (NMDOT) District Two
Description: The New Mexico Department of Transportation seeks bids for a price agreement supplying ready-mixed Portland cement concrete (D-2) in several classes for delivery across Curry, Roosevelt, Guadalupe, De Baca, Lea, Lincoln, Chaves, and Otero counties. The scope includes countywide destination delivery, admixtures and fiber reinforcements, and related demurrage, short-load, and mileage-based hauling charges. Bidders must be prequalified by NMDOT and provide product approvals, bonds, and insurance; the agreement has an initial one-year term with up to three additional one-year extensions.
StateAgency · NM, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
399 days before RFP
NMDOT reported fully funded roadway reconstruction and widening projects in the Jal area scheduled for letting in October.
Uh major construction projects in district 2. Um the control number 210 4333 and 34 are uh roadway reconstruction and widening down um in Jal area. Uh the construction cost for both of those projects is $100 million fully funded. Um those projects are also letting in October. Um next project is
State Transportation Commission Meeting
Board meeting · Sep 18, 2025
Strategic plan
263 days before RFP
NMDOT identified a four-year Section 130 programme of grade-crossing construction and engineering projects with stated expected obligations, including work in Mora, Raton, Folsom and the Carlsbad corridor.
Railway-Highway Crossing Program (Section 130) The FHWA Railway-Highway Crossing Program, commonly referred to as the Section 130 program, is primarily used to design and construct grade crossing safety improvements that can be developed and implemented more rapidly than most FHWA highway projects. Shown below in Tables 4-3, 4-4, 4-5, and 4-6 are yearly…
New Mexico Department of Transportation State Rail Plan 2025-2045
Board meeting
154 days before RFP
NMDOT District 2 planned to let the final phase of downtown Clovis roadway reconstruction in summer 2026.
downtown Clovis phase two, a full roadway reconstruction at a $42 million. We are going to finish the final phase of Clovis letting. We're going to let this summer. So, that will be another $42 million invested in that will complete the reconstruction of downtown Clovis on US 60.
State Transportation Commission Meeting
Board meeting · May 21, 2026
Board meeting
7 days before RFP
NMDOT staff anticipated 2026B bond funding for three roadway projects planned for letting in calendar year 2027.
today we're going to uh get um approval for our December bond sales. As you all are aware, we're anticipating 130 million um for our December sale. Uh we are uh moving to NMFA approval next week after approval from um commission today. Uh we'll be pricing the week of 11:116 and again closing the the week of 127. Um, just a reminder, the projects that we…
State Transportation Commission Regular Meeting
Board meeting · Oct 15, 2026
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (16 days left)
Strategic plan · Feb 1, 2026
Um next project is 210352. That's phase 2 of downtown Clovis urban reconstruction. Uh construction cost is 48.6 million. It's fully funded and it's going out next October 2026.
State Transportation Commission Meeting
Board meeting · Sep 18, 2025
Decision makers connected to this RFP from New Mexico Department of Transportation.
Adjacent opportunities open for bidding right now.
New Mexico General Services Department
State AgencyNM
Posted
Oct 22, 2026
Nov 24, 2026
Ready Mixed Portland Cement Concrete for the New Mexico Department of Transportation (NMDOT) District Two
Pennsylvania Department of General Services
State AgencyPA
Posted
Feb 29, 2024
Jul 31, 2029
Ready mixed concrete and cement/concrete products.
CityCA
Posted
Nov 2, 2026
Dec 3, 2026
The City of Lancaster seeks bids for the as-needed supply and delivery of Portland Cement Concrete Materials (PCC). Materials must meet the IFB requirements and be delivered to locations designated by the City as orders are placed. The resulting purchase order is scheduled to run from July 1, 2026, through June 30, 2027, with options for two additional one-year terms.
CityAL
Posted
Oct 20, 2026
Nov 16, 2026
Supply ready-mix concrete in specified strengths, with and without fibre reinforcement, including delivery as specified.