Purified Water Replenishment SJV Advanced Water Purification Facility RFP
Purified Water Replenishment SJV Advanced Water Purification Facility.
Description: Eastern Municipal Water District is soliciting construction bids for the San Jacinto Valley Advanced Water Purification Facility and associated brine ponds. Schedule A covers site work, the process building, ultrafiltration and reverse-osmosis equipment, piping, and electrical and control systems. Schedule B covers brine-pond civil works, liners, evaporation equipment, and electrical, instrumentation, and control systems.
SpecialDistrict · CA, US
Adjacent opportunities open for bidding right now.
Eastern Municipal Water District
Special DistrictCA
Posted
Aug 25, 2026
Nov 19, 2026
Purified Water Replenishment SJV Advanced Water Purification Facility.
CityCA
Posted
Oct 15, 2026
Nov 13, 2026
The City of Ontario is seeking proposals from qualified consulting engineers to expand on feasibility-study recommendations and prepare a preliminary design report for the Pure Water Ontario Advanced Water Purification Facility. The work includes project management, quality assurance and quality control, 30% construction-level plans, permitting support, and assistance with a USBR Title XVI grant application, with optional pilot-plant design. The facility design covers membrane filtration, reverse osmosis, UV/AOP, and injection wells for up to 4,500 acre-feet per year of purified water; the posting is for engineering consulting services, not a grant program.
CityID
Posted
Oct 13, 2026
Nov 2, 2026
The City of Idaho Falls is seeking sealed proposals or quotes for inventory replenishment for its Water Division. Proposals must be submitted through BidNet no later than 3:00 p.m. MST on November 2, 2026. The bid opening is scheduled for November 2, 2026, at 308 Constitution Way in Idaho Falls.
Alabama Department of Environmental Management
State AgencyAL
Posted
Jul 30, 2026
Sep 30, 2027
Procurement of bi-annual maintenance services for the Evoqua Purified Water System at ADEM's Birmingham Field Office laboratory, including inspection, operational function logging, and replacement of expendables, chemicals, and filters.
Decision makers connected to this RFP from Eastern Municipal Water District.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
160 days before RFP
EMWD reported completion of the AWPF final design and continued conveyance-pipeline design and construction-permit coordination ahead of construction.
Uh just to highlight a couple of accomplishments here as I wrap up on our p our purified water replenishment project. We completed the dis the the final design of our AWPF and we are getting ready to advance that to construction here uh most likely uh next quarter. Uh we are also continuing to advance the uh design of the conveyance pipelines and working…
Eastern Municipal Water District Board Meeting
Board meeting · Mar 18, 2026
Board meeting
83 days before RFP
EMWD reported that the AWPF was expected to advertise for construction later in June 2026 and the conveyance pipelines in May 2027.
These are schedules for the the two subjects. The AWPF project is anticipated to advertise for construction later this month. There'll be a three-year project duration for completion in September 2029. The conveyance pipelines will advertise for bidding in May of next year, but complete ahead of the AWPF in February of 2029.
Eastern Municipal Water District Board Of Directors Regular Meeting
Board meeting · Jun 3, 2026
Board meeting
83 days before RFP
EMWD approved Butier Engineering's construction-management contract for the Purified Water Replenishment Program.
A. Approve and Authorize Award of Contract with Butier Engineering ($7,929,322) for Construction Management of the Purified Water Replenishment Program, and Additional Appropriation of $7,929,322 (Voelz Alexander/Kokotas) Mr. Kokotas provided a presentation on this item RESULT: APPROVED \[3 TO 0\] MOVER: Philip E. Paule, Board Member EMWD Minutes Board of…
Eastern Municipal Water District Board Of Directors Regular Meeting
Board meeting · Jun 3, 2026
Board meeting
69 days before RFP
EMWD approved closing resolutions to finalize state grant and low-interest financing agreements for the AWPF and conveyance-pipeline and blending-facility projects.
On to item E. They adopt proposed closing resolutions to support Eastern Municipal Water District's two agreements with the state water resources control board for the purified water replenishment advanced water purification facility and purified water replenishment conveyance pipeline and blending projects. Nichollet. >> Yes, thank you. Good morning,…
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (24 days left)
Eastern Municipal Water District Regular Meeting
Board meeting · Jun 17, 2026