CityMS
Posted
Oct 15, 2026
Nov 24, 2026
Cannon Road Proposed Bridge RFP
Work inlcudes improvements include the installation and construction of new pre-cast bridge.
Description: Work includes construction of a new Amtrak station including a 17-space vehicular parking lot, sidewalks, station platform, canopy, lighing, earthwork, traffic control, erosion control and other incidental items and work.
City · MO, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
185 days before RFP
The minutes recorded that SCI was core drilling for the Amtrak station, construction plans were nearing submission, and $180,000 had been reimbursed for the project.
7. Communication From City Manager City Manager Melkus advised the Council that Kimes is finishing up the manhole project. The grant for the new playground at Moutlon Street Park has been applied for. SCI was doing core drilling for Amtrak, and we are close to submitting our construction plans. So far, the city has received $180,000.00 reimbursement for…
De Soto City Council Regular Meeting
Board meeting · Apr 20, 2026
Board meeting
129 days before RFP
The minutes recorded that 30% of the Amtrak construction and engineering plan was ahead of schedule, with final plan and ADA-accessibility work still required.
7. Communication From City Manager City Manager Melkus advised the council that thirty percent of the construction and engineering plan for Amtrak is ahead of schedule. Once this is complete, they just have to finalize the plans and make sure it's passed the building codes for ADA accessibility.
De Soto City Council Regular Session
Board meeting · Jun 15, 2026
Board meeting
66 days before RFP
The minutes recorded that 60% of the Amtrak plans had been presented and construction plans were the next phase, with the ADA platform still being worked out.
7. Communication From City Manager City Manager Melkus updated the council on the progress on Blow Street and how in two or three weeks the project should be completed. The quarterly meeting with Amtrak was held and sixty percent of the plans were presented and we are working out the ADA platform. The next phase is the construction plans.
De Soto City Council Regular Session Minutes
Board meeting · Aug 17, 2026
Board meeting
31 days before RFP
The minutes recorded that 60%-complete Amtrak station plans had been submitted, with Amtrak and Union Pacific approval pending before a planned bid before year-end.
City Manager Melkus advised the Council that the Amtrak station plans were submitted due to being sixty percent complete. At this point, we are waiting for Amtrak and Union Pacific to approve them so we can put the project out for bid . We would like to get the bid sent out before the end of the year. Mayor Smith asked how long the process takes to get…
De Soto City Council Regular Meeting
Board meeting · Sep 21, 2026
RFP published
Proposals due (22 days left)
Decision makers connected to this RFP from City of De Soto.
Adjacent opportunities open for bidding right now.
CityMS
Posted
Oct 15, 2026
Nov 24, 2026
Work inlcudes improvements include the installation and construction of new pre-cast bridge.
Chester Union Free School District
School DistrictNY
Posted
Oct 1, 2026
Nov 5, 2026
Work includes proposed athletic facility.
FederalWV
Posted
Oct 16, 2026
Nov 2, 2026
The U.S. Coast Guard proposes a sole-source, one-year purchase from National Law Enforcement Telecommunication System (NLETS), Inc. for access to the NLETS network for investigative and vessel-identification queries. The service supports criminal-background, warrant, identity, and investigative queries, and the agency says it believes no other source can satisfy the requirement. This is a special notice rather than a request for competitive quotations; responsible sources may email capability and qualification information by November 2, 2026, at 11:00 a.m. EST.
CityPA
Posted
Oct 8, 2026
Nov 5, 2026
Interior renovation of City.+The project includes the demolition and reconstruction of the bunk room, restroom/showers and two offices at both stations. An overview of the proposed work includes but not limited to: partitions, doors, interior glazed openings, architectural built-in casework, painting, plumbing fixtures, domestic water and sanitary waste distribution, and connection to existing systems, redistribution of existing HVAC, electrical service redistribution and connection to existing system and interior lighting.