Description: The procurement, installation and start-up of a calcite filter and ion exchange water softener. Also included is the modification of the well head for the facility. The work generally consists of the following: mechanical, electrical, process and plumbing, site work and instrumentation and control.
City · RI, US
From the first pre-RFP signals to the published RFP and its files.
Strategic plan
729 days before RFP
The adopted Comprehensive Plan calls for continued funding efforts to complete necessary upgrades and improvements to the City's water and wastewater treatment facilities.
WHAT WE'RE GOING TO DO GOAL NR-1: Protect and improve the quality of the City's natural environment. POLICY NR-1.1: Support efforts to improve the water quality of the Blackstone River and its tributaries. ACTION NR-1.1a: Continue to seek funding to complete necessary upgrades and improvements to the water and wastewater treatment facilities.
City Of Woonsocket Comprehensive Plan 2024-2044
Strategic plan · Oct 7, 2024
ACTION NR-1.1a Continue to seek funding to complete necessary upgrades and improvements to the water and wastewater treatment facilities. Public Works Finance Department Ongoing
City of Woonsocket Strategic Plan
Strategic plan · Aug 25, 2025
RFP published
Proposals due (6 days left)
Adjacent opportunities open for bidding right now.
California Department of Corrections and Rehabilitation
State AgencyCA
Posted
-
Jan 7, 2027
In general, the California Health Care Facility (CHCF) Potable Water Treatment System (PWTS) project will construct a new chlorination boosting system to supplement the disinfection of potable water delivered by the City of Stockton. The project will construct a PWTS consisting of an above ground chemical storage tank, chemical injection system with required electrical, mechanical, metering and control equipment. An approximately 900 square foot pre-engineered metal building, with site work and utilities, will also be constructed to house the chemicals and associated equipment. Integration of the new Supervisory Control and Data Acquisition (SCADA) system with the existing SCADA system is also required. Upon completion, the project must ensure compliance with the Environmental Protection Agency (EPA) and State Water Resources Control Board (SWRCB) drinking water quality standards related to chlorine residual at CHCF.
Northeast Mississippi Regional Water Supply District
Special DistrictMS
Posted
Nov 18, 2026
Dec 16, 2026
Purchase of ammonia for a potable water treatment plant of 18 mgd capacity.
Northeast Mississippi Regional Water Supply District
Special DistrictMS
Posted
Nov 18, 2026
Dec 16, 2026
Purchase of alum for a potable water treatment plant of 18 mgd capacity.
Federal06
Posted
Nov 6, 2026
Dec 29, 2026
Please refer to the attached solicitation.