Summary
Project consists along with all related sitework and new site infrastructure for the project. The site work will also need to be priced in two different scenarios as per the rfp document. Scenario 1: mass grading/full infrastructure this would entail the release of: (a) the road a - sections 2 & 3 plan; (b) the mass grading of the whole site; (c) pump station #2; (d) pitchkettle road widening; (e) pitchkettle waterline extension. Scenario 2: sub-phased infrastructure; this staggered approach would include the initial buildout of: (a) road a - sections 2 & 3; (b) the grading for strictly building 6, 10, ponds 9, 10 & 11, and road a, as shown in included building 6 & 10 cad surfaces and highlighted in the 2026. 04. 22 master plan markup subphase 6 & 10 ; (c) pump station #2 the construction of pitchkettle road widening and the pitchkettle waterline would be completed with the later buildings in this scenario.