County Of Menominee
The contractor shall provide all necessary materials, supplies, & equipment and perform all necessary services to replace four (4) HVAC rooftop units. Including but not limited to: removal and disposal of four (4) existing HVAC rooftop units. Disconnecting DDC wires from existing units. Disconnecting gas lines from existing units. Install curb adapter for new HVAC rooftop units. Provide and install four (4) new HVAC rooftop units. Reconnect gas lines. Reconnect DDC wires. Install new p-trap for each new roof top unit. Any repairs/patches necessary to the roof. See attached file.
rfp_fy2024-4_jail_hvac_project
Release
Sep 30, 2024
Close
Oct 17, 2024