Open RFPINVITATION FOR BIDS (IFB)
SOLICITATION NO. 2026-FS35-IFB02
FIRE STATION 35 INTERIOR REMODEL \& SITE IMPROVEMENTS
Description: ISSUING AGENCY: Northern Arizona Fire District
LOCATION: 9667 Concho Dr, Kingman, AZ 86409
PROJECT MANAGER: Fire Chief Brian Grant
CONTRACT DURATION: 120 Calendar Days to Substantial Completion
MAXIMUM BUDGET: $300,000.00 (Base Bid + Prioritized Alternates)
SECTION 1: PROCUREMENT SCHEDULE & INSTRUCTIONS
1.1 SCHEDULE OF EVENTS:
Legal Advertisement Dates: October 26 & November 2, 2026
Mandatory Pre-Bid Walk-Through: November 10, 2026, at 10:00 AM MST
Deadline for Written RFIs: November 17, 2026, by 5:00 PM MST
Final Addendum Issued: November 20, 2026
Sealed Bid Submission Deadline: December 3, 2026, at 2:00 PM MST
Public Bid Opening: December 3, 2026, at 2:05 PM MST
Board Contract Award Date: December 16, 2026
1.2 ELIGIBLE CONTRACTOR LICENSES:
Bidders must hold an active Arizona Registrar of Contractors Commercial or Dual License in
good standing: Class B-1 (General Commercial), Class B-2 (Small Commercial), Class KB-1
(Dual Building), or Class KB-2 (Dual Building). Residential-only licenses (Class B, B-3, or R-
series) are prohibited and non-responsive.
1.3 SUBMISSION REQUIREMENTS:
Bids must be submitted in a sealed envelope marked:
"SEALED BID - IFB NO. 2026-FS35-IFB02: STATION 35 REMODEL"
Deliver to: Northern Arizona Fire District, Attn: Chief Brian Grant, 2600 E Northern Ave,
Kingman, AZ 86409.
SECTION 2: DETAILED SCOPE OF WORK
The Contractor shall furnish all labor, materials, equipment, tools, commercial building permits,
and supervision required to execute the following scope of work at Station 35:
2.1 BASE BID SCOPE (INTERIOR RENOVATIONS, FINISHES & SYSTEMS)
1. Permitting & Regulatory: Pull all required commercial building permits from Mohave
County Development Services. All work must comply with local commercial building,
electrical, mechanical, and plumbing codes.
2. Demolition & Wall Alterations:
• Demolish designated non-structural interior partitions and fixtures.
• Saw-cut and trim one (1) open pedestrian walkthrough passage through an
existing non-bearing CMU wall. (Zero structural or load-bearing modifications).
• Gear Room Exterior Wall: Remove existing exterior garage door at the Gear
Room location, in-fill and wall off the opening matching exterior construction,
and install one (1) standard exterior commercial pedestrian door in the new wall.
3. Exterior Door Modification: Replace one (1) existing exterior door assembly with a code-
compliant commercial outward-swinging exterior door with panic hardware/weather-
stripping.
4. Framing, Drywall, Paint & Trim (Facility-Wide):
• Bunk Rooms: Frame, drywall, tape, texture, prime, paint, and trim four (4)
individual crew bunk rooms. Saw-cut/frame exterior wall openings and install
four (4) new exterior windows (one per bedroom) with exterior
trimming/flashing.
• Gear Room: Remove garage door. Reframe to match exterior wall. Install single
exterior swing door to framed wall.
• Kitchen & Day Room: Complete remodel including drywall, tape, texture, prime,
paint, baseboard/casing trim, new cabinetry, commercial/heavy-duty residential
countertops, plumbing fixtures, and appliances.
• Report Room & Gym: Complete finish remodel including drywall repairs, tape,
texture, prime, paint, and trim. Gym subfloor shall be floated and leveled to align
smoothly with adjacent finished floor elevations.
• Restrooms: Remove one (1) existing restroom completely; frame, drywall
(moisture-resistant cement/greenboard in wet zones), tape, texture, prime, paint,
and trim two (2) new full bathrooms (requiring floor slab trenching) and
reconfigure one (1) existing restroom into a half bathroom.
• Dedicated Rooms: Construct dedicated Turnout Gear and Laundry rooms,
complete with drywall, tape, texture, prime, paint, baseboard trim, and utility
rough-ins (exhaust airflow and washer/extractor connections).
• General Drywall & Finish Standard: Install new drywall across all new framed
additions and replace damaged/existing drywall facility-wide as needed. Apply
smooth or light orange-peel texture, one (1) coat of commercial primer, and two
(2) coats of washable commercial-grade paint (semi-gloss/satin).
• Furnish and install commercial-grade baseboards, door casings, and trim
throughout all remodeled spaces.
5. Mechanical, Electrical & Low-Voltage Audio:
• Electrical & Receptacles: Ensure full electrical service, commercial LED lighting,
and duplex/GFCI receptacles in EVERY newly framed or remodeled room and
space.
• Ceiling Fans: Furnish and install heavy-duty commercial ceiling fans with wall-
mounted speed controls in all four (4) crew bunk rooms.
• HVAC: Ensure conditioned HVAC supply and return air is present in ALL living
and sleeping spaces.
• Station Paging/Audio System: Furnish and install commercial ceiling-flush
speakers wired to the station audio/paging system in the following locations:
i. 4 Crew Bunk Rooms (each equipped with individual wall-mounted rotary
attenuator volume controls)
ii. 1 Gym Room
iii. 3 Bathrooms
iv. Kitchen
v. Day Room
vi. Main Entryway / Lobby
(Speakers and wiring must interface seamlessly with District alerting/paging head-end
equipment).
6. Epoxy Flooring:
• Surface prep, grinding, subfloor patching/leveling, and application of seamless
commercial concrete epoxy flooring throughout living, operational, and
transitional spaces.
7. Operational Continuity: Station 35 remains fully operational 24/7/365. Contractor must
install dust and noise containment barriers and maintain zero obstruction to active
emergency response egress or apparatus bay doors.
2.2 ADDITIVE BID ALTERNATES (EXTERIOR & SITE IMPROVEMENTS)
Alternates will be evaluated and awarded in numerical order up to the available $300,000.00
budget cap:
• ADDITIVE ALTERNATE NO. 1:
o Apparatus Bay Concrete Apron Replacement. Complete demolition and re-pour of
heavy-duty reinforced concrete apparatus bay apron pad.
• ADDITIVE ALTERNATE NO. 2:
o Exterior Station & Bay Door Painting. Complete exterior surface prep, pressure
washing, priming, and painting of the main station structure, including all exterior
trim and two (2) main apparatus bay overhead doors.
• ADDITIVE ALTERNATE NO. 3:
o Asphalt Paving, Parking Lot & Driveway Improvements
o Construct/pave new asphalt driveway extending from the main road to the
employee parking area.
o Construct/pave new asphalt parking lot structured to accommodate 7 to 8
employee/visitor vehicles.
o Perform asphalt repairs, crack sealing, leveling, and seal-coating from the
concrete apparatus pad to the main road.
• ADDITIVE ALTERNATE NO. 4:
o Concrete Side Exterior Crew Patio Form, reinforce, and pour concrete side
exterior patio pad for off-duty firefighter crew use.
SECTION 3: STATUTORY & LEGAL TERMS
1. BID SECURITY (A.R.S. § 34-201): Bids must be accompanied by a Bid Bond, Certified
Check, or Cashier's Check equal to 10% of the total combined bid amount, payable
to Northern Arizona Fire District.
2. PERFORMANCE \& PAYMENT BONDS (A.R.S. § 34-221): The awarded contractor must provide 100% Performance and 100% Payment Bonds prior to contract execution.
3. STATUTORY RETENTION (A.R.S. § 34-221): 10% retention withheld from monthly progress payments.
4. CONTRACT AWARD METHODOLOGY: Contract awarded to the lowest responsive and responsible bidder for the Base Bid plus as many Additive Alternates 1-4 as fit strictly within the $300,000.00 budget cap.