HL-0027 - GRADING, DRAINAGE, PAVING, AND SIGNALS AT SR 1301 (SUNSET LAKE ROAD) WIDENING FROM US 401 TO SR 1431 (PRODUCTS ROAD) RFP
Roadway widening construction involving grading, drainage, paving, and signal work.
Description: The Town of Fuquay-Varina seeks a contractor to widen Sunset Lake Road (SR 1301) as part of the Phase II project, including adding travel lanes across the Norfolk Southern Railroad and improving traffic operations at the US 401/North Main Street intersection. Work includes grading, drainage, paving, traffic signal improvements, pavement markings, signage, and other associated improvements. The contractor must provide all labor, materials, and incidental items necessary to complete the described improvements.
City · NC, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
315 days before RFP
The Town reported that Sunset Lake Road widening right-of-way acquisition was underway, with construction anticipated in late summer or early fall 2026 after right-of-way and permitting authorization.
o Engineering Department -- The right-of-way acquisitions are underway for three transportation projects, the Sunset Lake Road widening, the Hilltop Needmore/Bass Lake Sunset Lake Road intersection and the Old Honeycutt Highway 55 intersection project. Construction for these three projects is anticipated to start in late summer early fall of 2026 once…
Fuquay-Varina Town Board Meeting Minutes
Board meeting · Jan 5, 2026
Board meeting
105 days before RFP
The Town reported completed right-of-way acquisition and submitted final plans for Sunset Lake Road Widening HL-0027, with construction advertisement expected in late 2026 pending NCDOT/FHWA approvals.
Sunset Lake Road Widening (HL-0027): Right-of-way (ROW) acquisition is complete. Final plans have been submitted for approval, and an advertisement for construction is expected late 2026, pending final NCDOT/FHWA approvals.
Fuquay-Varina Town Board Regular Meeting
Board meeting · Aug 3, 2026
Board meeting
69 days before RFP
The Town reported completed right-of-way acquisition and requested FHWA construction authorization for Sunset Lake Road Phase II, with advertisement planned after authorization and construction anticipated in early 2027.
11.A Manager's Report Town Manager Mitchell gave the following additional updates: o Public Utilities Department -- The department has conducted its lead and copper sampling of the water distribution system. All samples came back "good" and in compliance. o Engineering Department -- Duke Energy is completing utility relocations at the Old Honeycutt at NC55…
Fuquay-Varina Town Board Regular Meeting Minutes
Board meeting · Sep 8, 2026
Board meeting
14 days before RFP
The Town reported receipt of FHWA construction funding authorization for Sunset Lake Road Phase II, finalization of bid documents, and anticipated construction in summer 2027.
improves. the Sunset Lake Road phase 2 widening project. We've received construction funding authorization on that project from the Federal Highway Administration. Staff is finalizing bid documents for advertisement. Construction is anticipated to commence in the summer of 2027.
Board of Commissioners Board of Commissioners Meeting
Board meeting · Nov 2, 2026
RFP published
Proposals due (50 days left)
Decision makers connected to this RFP from Town of Fuquay-Varina.
Adjacent opportunities open for bidding right now.
CityNC
Posted
-
Jan 12, 2027
Roadway widening construction involving grading, drainage, paving, and signal work.
CityCA
Posted
-
Dec 15, 2026
Work consists of excavation and embankment for roadway improvements; remove existing and construct new asphalt paving. Modify and extend existing and construct new storm drains, and appurtenant structures; subsurface utility locating and potholing, excavation and trenching, abandon waterline remove existing conflicting waterline, construction of new waterline and appurtenances, construction of waterline connections to existing waterlines, installation of waterline fittings and valves, construction of new water service connections, construction of sample port, construction of slurry backfill for protection and support of utility, relocation of water meters and double detector checks, filling, flushing and hydrostatic testing all water mains and appurtenances, construct new traffic signals and appurtenant structures; construct ada curb ramps; construct new asphalt concrete dikes; construct new sound walls; install pavement markings, signage, and striping.
CountyTN
Posted
Nov 12, 2026
Dec 16, 2026
DUE TO THE NATURE OF THIS SOLICITATION, VENDORS WILL NOT BE PERMITTED TO RESPOND ELECTRONICALLY. PLEASE SELECT UNDER THE "ATTACHAMENT" SECTION THE PDF FILE OF THE DOCUMENT. YOU CAN PRINT THE COMPLETE SOLICITATION AND RESPOND ACCORDINGLY. BIDS MAY BE SUBMITTED BY HAND OR COMMERCIAL CARRIER. Invitation for Bids 3782 for the provision of BAKERTOWN ROAD REALIGNMENT AND WIDENING - PHASE I. Due to the nature of this bid, vendors will not be permitted to respond electronically. Please select under the "Attachment" section the PDF file of the document. You can print the complete solicitation and respond accordingly. Bids may be submitted by hand or commercial carrier. Please direct all inquiries to Brian Hubbs at 865.215.5753.
CountyFL
Posted
Nov 9, 2026
Dec 9, 2026
The project shall consist of the widening and resurfacing of County Road 12 from South of Zebbie Odom Road to Lake Mystic Road for approximately 2.862 miles in Liberty County, Florida.