Summary
Interior buildout for park community center. Metal building is erected on floor slab with plumbing rough in. Exterior doors are to be reframed under separate contract to receive h.m, frame and steel
doors—h,m, frame and steel doors and hardware are to be included in bid. Contract for plumbing rough in and top out has been issued to LAV plumbing by the county. Successful bidder is to coordinate completion of plumbing with LAV plumbing (478-445-4791). Wood framing is acceptable in place of metal framing. Storage room is required to be one-hour fire rated. Door and h.m. frames are required to
be 45-minute rated. Frame ceiling of storage room with 2’x10” #2 pine framing, deck with 3/4” plywood. Locate water heater and mechanical units on floored area above storage room. Install two residential hoods over stoves vented to exterior. Install residential fire
suppression systems in both hoods. Stoves and kitchen equipment supplied under separate contract. Door 101 is being supplied by Oconee Glass under separate contract, (contact Tommy
Aycock to coordinate installation 489-456-3283). All exterior doors are to receive door closer, lever lockset with lock guard, and hinges. All locks are to be keyed per instructions by County. Restroom doors 103 and 106 are to receive privacy lock and door closer.