Summary
Bid Package 3: The majority work of this contract is generally described as follows: 130,000 CY Topsoil Stripping & Stockpiling; 135,000 CY Onsite Excavation/Fill/Compaction; 30,000 CY Offsite Fill/Compaction; 62,000 CY 6" Topsoil Respread; 17,100 LF Silt Fence; 130 Ditch Checks; 30 Rock Check Dams; 8,300 SY Channel Erosion Mat; 46,900 SY Non-Channel Erosion Ma; 62.6 AC Temporary Seeding; 62.6 AC Permanent Seeding/Fertilizer/Mulch; Outlet Controls for Ponds C, D, F, and G; Emergency Spillways for Ponds C, D, F, and G; 16,500 CY 2’ Type A Clay Pond Liner; 1,500 8” Drain Tile; 5 Drain Tile Manholes; 320 LF Temporary Culvert; 1 Temporary Crossing.