Special DistrictFL
Posted
Nov 5, 2026
Dec 4, 2026
Underground Padmount Transformer and Switchgear Inspections
Underground Padmount Transformer and Switchgear Inspections
Description: Procure double-sided padmount solid-dielectric insulated switchgear with integrated automation as replacements for its 12 kv live-front, air-insulated padmounted switchgear.
City · CA, US
From the first pre-RFP signals to the published RFP and its files.
Strategic plan
APU's 2025 Wildfire Mitigation Plan proposed replacing live-front distribution switches with dead-front solid-dielectric switches during 2026-2027.
15 Surface-mounted Solid Dielectric Switches Replace live-front distribution switches w/ dead- 2026-2027 $1000 https://www.anaheim.net/763/Residential-TreePower.%20In%202024 https://www.anaheim.net/763/Residential-TreePower.%20In%202024 https://www.anaheim.net/4752/Mylar-Balloons https://www.anaheim.net/4752/Mylar-Balloons 73 APU's Wildfire Mitigation…
Anaheim Public Utilities Department Wildfire Mitigation Plan 2025
Strategic plan · 2025
In August 2024, a small vegetation fire (approx. 600 ft2 in size) caused by an animal intrusion resulted in a flashover inside an APU surface-mounted, high-voltage distribution cabinet. AF&R crews quickly extinguished the fire. As a result, APU developed a mitigation measure to increase the vegetation clearance around surface-mounted equipment within the…
Anaheim Public Utilities Department Wildfire Mitigation Plan 2025
Strategic plan · 2025
Budget
484 days before RFP
Anaheim's adopted FY 2025/26 budget includes an ongoing citywide program for substation, automation, and protection work, including replacement of aging switches.
Substation, Automation, and Protection Total Project Cost: Ongoing Construction Period: Ongoing Funding Source: Electric Utility Enterprise Funds Project Location: Citywide Strategic Plan Goal: FY 2025/26 Adopted FY 2026/27 Projected FY 2027/28 Projected FY 2028/29 Projected FY 2029/30 Projected 5-Year Total $14,808,000 $33,750,000 $38,850,000 $23,800,000…
Board meeting
127 days before RFP
APU reported a $7.5 million state grant to accelerate procurement and implementation of a new high-voltage switch.
Notably, a seven and a half million dollar state grant will accelerate procurement and implementation of a new type of high voltage switch to strengthen grid reliability. And the
Anaheim City Council Council Meeting
Board meeting · Jun 23, 2026
Projects in this category support grid modernization and reliability improvements. APU received notification of a state grant award that will support the installation of high-voltage switches that no longer use gas as the insulating medium. Funds expended on this project will be reimbursed through the grant.
Budget
119 days before RFP
The adopted FY 2026/27 CIP includes ongoing citywide substation upgrades and replacements of aging equipment, including switches.
Substation Projects Total Project Cost: Ongoing Construction Period: Ongoing Funding Source: Electric Utility Enterprise Funds Project Location: Citywide Strategic Plan Goal: � � � � � FY 2026/27 Adopted FY 2027/28 Projected FY 2028/29 Projected FY 2029/30 Projected FY 2030/31 Projected 5-Year Total $13,140,000 $20,350,000 $19,480,000 $25,480,000…
City of Anaheim FY2026-27 Budget
Budget · Jul 1, 2026
RFP published
Proposals due (22 days left)
City of Anaheim FY2025/26 Budget
Budget · Jul 1, 2025
City of Anaheim FY2026-27 Budget
Budget · Jul 1, 2026
Decision makers connected to this RFP from City of Anaheim.
Adjacent opportunities open for bidding right now.
Special DistrictFL
Posted
Nov 5, 2026
Dec 4, 2026
Underground Padmount Transformer and Switchgear Inspections
Metropolitan Wastewater Reclamation District
Special DistrictCO
Posted
Oct 13, 2026
Nov 12, 2026
Seeking qualified and experienced firms capable of providing preventive maintenance, inspection, testing, and servicing of critical electrical distribution equipment.
Minnesota State University Mankato
Higher EducationMN
Posted
Oct 30, 2026
Dec 1, 2026
Project will replace the original switchgear responsible for transferring power generation from the Xcel utility service to the campus standby generators.
Special DistrictFL
Posted
Nov 5, 2026
Dec 4, 2026