Description: DESIGN-BUILD Service - Dry Standpipe System Replacement.
SpecialDistrict · PA, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
386 days before RFP
The SEA Board approved a $34,300 DESMAN facility condition assessment for North Shore Garage to identify deficiencies, future capital projects, and repair or replacement costs.
Ms. Frisbie stated The Stadium Authority (SA) and the Authority collectively own three garages (NSG, West General Robinson Street Garage (WGRSG), and Gold 1 Garage (GIG)) on the North Shore. The NSG (the Authority) opened in 2001. The WGRSG (SA) opened in 2006, and GIG (SA) in 2017. The Authorities have invested in multiple capital projects to extend the…
Sports & Exhibition Authority of Pittsburgh and Allegheny County Meeting Minutes
Board meeting · Oct 9, 2025
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (13 days left)
Adjacent opportunities open for bidding right now.
CityOH
Posted
-
Dec 1, 2026
Removal, disposal, and installation of a new standpipe at their water tower. The standpipe to be removed is a 24" insulated, concrete-lined ductile iron pipe (DIP). The length of pipe to be replaced and installed is approx. 125' (the contractor shall determine the exact length) and shall be like-in-kind to the existing standpipe.
CityCA
Posted
Oct 24, 2026
Nov 25, 2026
DESIGN-BUILD: photovoltaic (PV) solar energy system. Removal of existing photovoltaic system including all components. Procurement and installation of new PV system, startup testing and commissioning.
CitySC
Posted
Oct 14, 2026
Nov 19, 2026
The project generally consists of the installation of approx. 1,475 LF of 6" DIP waterline, 2 fire hydrants, valves, asphalt replacement, service reconnections, connections to the existing water system, and other necessary appurtenances and work tasks required for a complete installation.
FederalOH
Posted
Nov 6, 2026
Nov 20, 2026
DESIGN-BUILD - replace circuit F-01 from substation.
Decision makers connected to this RFP from Sports And Exhibition Authority Of Pittsburgh And Allegheny Co.