See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
From the first pre-RFP signals to the published RFP and its files.
2 files available
Meeting agenda
315 days before RFP
Water Resources proposed additional authorized representatives to process OWRB FAP-24-00019-L loan requisitions and disbursements for future construction of NE Complex - Phase 1 (Danforth Tower Relocation).
See sourceHide source
Item Consideration of Approval of Authorizing Additional Representatives to Execute Loan Fund Requisitions for Oklahoma Water Resources Board State Revolving Funds Promissory Note Series 2024C including the Director of Water Resources, Assistant Director of Water Resources, and the Senior Water Resources Engineer. (Citywide) Background The Oklahoma Water…
Edmond City Council and Public Works Authority Regular Meeting Agenda
The February 25, 2026 Public Works Committee agenda materials stated that WC24-00005, the NE Complex Phase 1 tank-relocation project, was 100% designed and expected to be ready for bid in late spring or early summer 2026.
See sourceHide source
Water WC24-00005: NE Complex - Phase 1 (Danforth Tower Relocation - TWR-3) Relocation of the existing 0.5 Danforth elevated storage tank to the new NE Complex. Offsite water and sewer line improvements along Sorghum Mill Rd are included. The 2013 Water Master Plan identified the need for improvements to storage and pumping facilities in the NE portion of…
City of Edmond Public Works Committee Regular Meeting
Meeting agenda
89 days before RFP
The Public Works Committee agenda proposed bidding the NE Water Storage Complex Phase 1 project to relocate a 0.5-million-gallon tank and construct associated water and sewer lines, with an $8.2 million-$9.825 million budget and anticipated OWRB FAP financing.
See sourceHide source
Information Item Consideration of Approval to Proceed with Bidding the WC24-00005 -- NE Water Storage Complex-- Phase 1 (Danforth Tower Relocation) project. (Ward 2) Background The 2013 Master Plan identified the need for water storage in the northeast portion of the water system. The first phase of the recommended Northeast Water Storage Complex is…
RFP published
WC24-00005 NE Complex Phase 1 (Danforth Tower Relocation)ZIP
This interior renovation is a Level 2 alteration. It will change an existing open office into an office suite with four individual offices and a meeting room.
Project includes the construction of a single lane roundabout and installation of storm sewer. The project also includes the construction of approx., 1,050' of shared use path and sidewalk construction.