Retrieving RFP details
Release
Close
Village of New Vienna
Work generally consists of installation of approx 1160 LF of 8" pvc water main in pavement by open cut; installation of nine (9) 8" gate valves; installation of three (3) fire hydrant assemblies; five (5) connections of installed water main to existing water mains; re-establishment of approx twenty-two (22) 3/4" service connections; 500 SY of roadway pavement restoration; add alternate #1 includes roadway full-width asphalt 1 mill & overlay.
City of Haines City
Work consists of replacement of water mains.
New Orleans Sewerage and Water Board
Sewer force main replacement project.
City of Wessington Springs
The major elements associated with the construction of the project are: 2,445 feet of 6-inch water main; 1,099 feet of 8-inch water main; 33 feet of encasement for water main; 30 water services with saddles, valves and connections; 857 feet of water service pipe; etc.
Release
Nov 04, 2025
Close
Nov 21, 2025