Nevada State Public Works Board
State AgencyNV
Posted
Nov 16, 2026
Dec 4, 2026
CMAR Selection for the Advance Planning: Culinary, Bakery & Laundry Building (Northern Nevada Correctional Center) (Request for Proposals)
The scope of the CMAR’s Pre-Construction Services includes, but is not limited to the following: 1. Participation in regularly scheduled design progress review meetings with the Architect and the Owner. The CMAR shall provide ongoing input with respect to constructability, construction cost, construction duration, sequence of construction, and construction means and methods. 2. Conducting investigations, with participation by appropriate subcontractors, of all existing site and building conditions, and all off-site conditions as appropriate for each project. 3. Assessment and advisement regarding schedule impacts related to long lead submittals and long lead equipment procurement.