Water System Improvements - Phase 1 (Advertisement for Bids)
Work includes furnishing all the labor, materials, and equipment for constructing approx 2877 LF of 6" waterline; 1559 LF of 4" waterline; 1921 LF of 2" waterline; associated directional drill installation where necessary; valves; hydrants; water service connections; amr ready water service meters; water service meter pits; connections to system; existing pipeline abandonment; grass seeding; gravel surfacing; concrete and asphalt pavement replacement; erosion control; water well metering upgrades; and all other incidental and appurtenant work required to complete the improvements as shown and specified.