Capital improvement plan
379 days before RFP
VDOT's initial financial plan recorded a planned I-81 widening construction contract with advertisement in October 2025, award in February 2026, and notice to proceed in March 2026.
2. SCHEDULE Conceptual design and project development for the I-81 Widening between MM 242.0 and 248.8 project began in February 2020. Public involvement included a Citizen Information Meeting held on September 14, 2021, the Design Public Hearing held on June 28, 2022, along with smaller meetings with stakeholders and local officials held thereafter. The…
Virginia Department of Transportation Initial Financial Plan 2026-2032
Capital improvement plan · Sep 30, 2025
Capital improvement plan
124 days before RFP
The FFY 24-27 live STIP lists $1,487,863 in FY24 AC-Other funding for VDOT's district-wide Plant Mix Schedule (PM-8H-23).
MPO Multiple MPOs UPC NO 120968 SCOPE Resurfacing SYSTEM Primary JURISDICTION Staunton District-wide OVERSIGHT NFO PROJECT #SGR23VP District Wide Plant Mix Schedule (PM-8H-23) ADMIN BY VDOT DESCRIPTION FROM: VARIOUS TO: VARIOUS (5.8500 MI) ROUTE/STREET 9999 TOTAL COST $1,487,863 FUND SOURCE MATCH FY24 FY25 FY26 FY27 CN AC Federal - AC OTHER $0 $1,487,863 $0…
2024-2027
Capital improvement plan · Jun 12, 2026
Capital improvement plan
124 days before RFP
The live STIP lists a $4,150,712 Culpeper District-wide primary-system asphalt-resurfacing project with CN funding.
UPC NO 121981 SCOPE Resurfacing SYSTEM Primary JURISDICTION Culpeper District-wide OVERSIGHT NFO PROJECT #SGR23VP PM-7G-23 Asphalt Resurfacing Primary System ADMIN BY VDOT DESCRIPTION FROM: Varies TO: Varies ROUTE/STREET VARIES (9999) TOTAL COST $4,150,712 FUND SOURCE MATCH FY24 FY25 FY26 FY27 CN Federal - NHS/NHPP $0 $1,750,000 $0 $0 $0 CN AC Federal - AC…
2024-2027
Capital improvement plan · Jun 12, 2026
Agenda packet
106 days before RFP
VDOT proposed Piney Forest Road reconstruction including asphalt milling and resurfacing, with construction planned for March 2029 through summer 2030.
The following schedule has been proposed for the project: • Public Hearing -- June 30, 2026 • Right of Way -- February 2027 • Advertise for Construct. Bids -- Fall 2028 • Construction Begins -- March 2029 • Construction Completed -- Summer 2030 This project includes the removal of 0.9-mile of continuous center turn lane and construction of a raised 14' wide…
Virginia Department Of Transportation Design Public Hearing
Agenda packet · Jun 30, 2026
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (14 days left)
Adjacent opportunities open for bidding right now.
Virginia Department of Transportation
State AgencyVA
Posted
Oct 13, 2026
Nov 18, 2026
2027 plant mix - primary.
Virginia Department of Transportation
State AgencyVA
Posted
Oct 13, 2026
Nov 18, 2026
2027 plant mix - primary.
Virginia Department of Transportation
State AgencyVA
Posted
Oct 14, 2026
Nov 18, 2026
412_FDR - 2027 PLANT MIX - PRIMARY/SECONDARY Location: Various (Prequalification Required) All questions must be submitted to VDOT using CABB. (Contractors Advertisement Bulletin Board)
Virginia Department of Transportation
State AgencyVA
Posted
Oct 14, 2026
Nov 18, 2026
353_SGR* - 2027 PLANT MIX - PRIMARY / SECONDARY Location: Various (Prequalification Required) All questions must be submitted to VDOT using CABB. (Contractors Advertisement Bulletin Board)
Decision makers connected to this RFP from Virginia Department of Transportation.