US Highway #9 Water Line Relocation RFP
Posted
Nov 19, 2026
Dec 10, 2026
Exploratory digging, 2" flush hydrant assembly w/2" GV, 3" PVC waterline, clearing & grubbing; 3" HDPE (DR-11), 3" & 1" gate valves; 3/4" service line & tuff tube testing; gravel, cut & replace; MJ fittings w/Midco restraints, water meter w/meter box; 1" Air release valve; 6" creek crossing encased in HDPE (DR-9) pipe; 3" C1" tapping saddle w/1" corp stop; 2" road bore encased in HDPE (DR-9) pipe; sampling station, right of way staking (LS).