Lower Fm-14 Bypass Force Main Replacement Project RFP
Jul 30, 2026
Closes
Sep 3, 2026
The project is generally described as follows: install new sewer force main by open trench (25 LF), install new sewer force main by horizontal directional drilling (511 LF), including sawcut, excavation and backfill, shoring, abandoning existing sewer pipelines and manholes, constructing new PCC vaults with combination air release valve and bypass assembly, asphalt concrete pavement restoration, CCTV inspection, traffic control, and project signs.