Repair of Cedar Creek Flood Prevention Dam No. 9 (Request for Proposal)
Posted
Oct 30, 2026
Dec 14, 2026
Clear, grub and revegetate areas along the upstream slope and between the downstream toe of the embankment to a point that is 20 feet downstream and reinstall fencing. Clear and grub around the plunge pool and reconstruct the plunge pool with earthfill and riprap armoring. Installation of shoreline wave protection in the form of riprap. Lime stabilization and regrading of the near surface soils along the upstream and downstream slopes to repair historic surface slides and stabilize the slopes. Repair minor erosion in lower part of auxiliary spillway. Replacing the low-level sluice gate and trash rack on the principal spillway riser structure regrading the auxiliary spillway control section.