West Maple Grove Road and Fivepointville Road Sanitary Sewer Repairs Contract No. 26-3 RFP
Posted
Nov 13, 2026
Dec 30, 2026
Construction services to perform various sanitary sewer infrastructure improvements and roadway restoration at multiple locations within the Authority’s sanitary sewer collection system. Work includes replacement of approximately 360 linear feet of 8-inch sanitary sewer with SDR-26 PVC, replacement of approximately 30 linear feet of 6-inch SDR-26 PVC lateral, replacement of about seven manhole composite riser rings, modification of an existing manhole drop connection, and PennDOT roadway pavement restoration at several locations. The contract also requires compliance with prevailing wage rules, Public Works Employment Verification Act (Act 127 of 2012), and use of U.S.-made steel for steel products.