Lehighton River Crossing Water Main Replacement
Jul 30, 2026
Closes
Aug 26, 2026
Installation of approx. 380 LF of 12" DIP water main and approx. 775 LF of 20” HDPE water main, and connecting to existing water main near Borough. The 12" DIP is to be installed via open excavation and includes 65 LF of water main crossing a levee. The 20" HDPE is to be installed via horizontal direction drilling. Project also includes water appurtenances, easement clearing, and abandonment of existing 6" water main.