Construction of 0.095 Miles of Box Bridge & Approaches On Card Road (c.r. 459) RFP
Posted
Nov 12, 2026
Dec 15, 2026
Work includes 34 LF removal of pipe (all sizes); 55 SY remove and relay riprap; 1,012 CY unclassified excavation (fm); 178 CY excess excavation (fm); 750 CY structure excavation; 500 SY geotextile fabric stabilization, type iii, non-woven, aos 0.43 mm; 1 EA temporary stream diversion; 142 TN granular material, (class 4, group "c"); 332 TN crushed stone, size 57; 924 TN crushed stone, size 610; 1,219 SY mixing, shaping and compaction; 92 TN hot mix asphalt, (st) (12/5 mm); 92 TN hot mix asphalt, (st) (9.5 mm); 0.166 CY class "b" structural concrete, minor structures.