23082AMLBAML Reclamation Project (Request for Bids) *REBID II*
Posted
Nov 21, 2024
Sep 22, 2026
As part of the initial phase of work, to contain the highwall, a shotcrete face was installed on the lower wall and a rockfall mesh on the upper wall, rock bolted where needed by GSI under state master agreement. As part of the secondary phase, an existing drainage path will be upgraded with a new under road pipe and rehabilitated rock ditch that discharges the water into existing drainage.