I-85 SSI Project Progress Meeting
The meeting provided a progress update on project activities, including recent cleanup efforts on 8th Street and monitoring of construction progress. Discussions focused on the upcoming work schedule for the next 30 days, particularly regarding the North Southern border crew, flagger scheduling, and potential work on C Street to optimize progress. The participants explored options for rock removal and pipeline installation, addressing challenges related to gas line proximity, vibration limits (PPV), and utility coordination, including the potential use of temporary service lines to facilitate construction.