Summary
Remove all the asbestos in the central pipe chase and to replace the fire main riser in the main hospital, Building 1. This project will remove friable asbestos-containing material within the main central chase of the hospital. Asbestos-containing material (ACM) is being removed to allow for the facilities primary fire main risers to be replaced. New fire main risers will be installed. Piping in the central chase will be re insulated. Project will require a multi-phase process to prevent asbestos related exposure and to allow for sampling and asbestos abatement. New fire main risers will need to be installed prior to removal of existing ones. Work includes general construction, demolition, architectural, mechanical, electrical, plumbing, medical gas, radiation protection, fire protection, telecommunication, and certain other items as required by provided construction documents.