Summary
Project includes mobilization of your equipment, providing traffic control including flagging as needed to complete the project, strip shoulders prior to adding base course gravel, remove, load, haul and dispose offsite of sod, grass, and deleterious material from shoulder. Pulverize the existing blacktop roadway full depth and width. Grade, shape, and compact pulverized material. Furnish, haul, place, rough grade, and compact stone base. Shape, final grade, water, and compact roadway. Pave with hot mix asphalt, with widened corners, and six-inch aprons on unpaved entrances. Saw cut all butt joints, intersections, and private entrances. Furnish, hull, place, and compact crushed stone base course shoulders on edges of roadway after paving.