Summary
Work includes construction of approx. 4,690 LF of 12" fusible pvc pipe by sliplining; 4,740 LF of 16" fusible pvc pipe by open cut downstream of the shore acres pump station site; rehabilitation of the existing flow meter vault at the pump station site involving the removal and replacement of the existing piping, the flow meter and other appurtenances; construction of a new 8-foot diameter, 12-foot high hydropneumatic bladder tank (surge tank) and supporting foundation at the shore acres pump station site; construction of a new concrete valve vault at the pump station site with two plug valves, an air vacuum valve assembly, access tees and a sump pump; etc, see outside link.