Summary
Rehabilitate a portion of its sanitary sewer system. The work will consist of a variety of trenchless pipe and manhole restorations with the goal of reducing the amount of groundwater infiltrating the system as well as improving the stability and resiliency of the sewer network. The bulk of the mainline rehabilitation will be Cured-in-Place-Pipe installations (full segment and sectional). Some mainline joint grouting will be included. The Manholes to be restored will either be lined with a Cementitious liner and/or be fully grouted. Some manholes will require grouted pipe connections or rebuilt chimneys. Work includes 12,880 F of 8-, 10-, 12- 18- and 36-inch Cured-In-Place Pipe lining; 2,500 F of 8-, 10-, 21- and 24" mainline joint grouting; Grouting ~150 lateral connections; Lining/Grouting of 72 manholes; and, Bypass Pumping.