Summary
Purchase, delivery, installation, startup, and commissioning of replacement aeration equipment for the track 37 aeration basin; installation of three (3) skid-mounted 125-hp multistage centrifugal blowers; demolish existing 6" discharge piping and replace in kind with 8" piping, valves, fittings, and pipe supports as indicated in the contract documents; demolish and replace all existing equipment pads based on proposed equipment dimensions and existing pipe elevations; upsize conductors and breakers on two (2) circuits for an increased load from 60- hp to 125-hp. Test all conductors and grounding wires in compliance with neta- ats; demolish one (1) existing 60-hp vfd panel and replace-in-kind with a matching eaton 125-hp vfd matching the existing vfd's currently installed. See attached file.