Summary
The City of St. Joseph (Missouri) requests proposals to process approximately 40,000 cubic yards of excavated shelf rock generated during ongoing cell construction at the St. Joseph Sanitary Landfill. The work may be performed via on-site crushing or off-site removal and requires the contractor to provide labor, equipment, mobilization, crushing/processing, hauling, dust control, permits, insurance, and compliance with applicable regulations; the project must be completed within 90 days of contract award. Proposals must be submitted electronically through the City's bidding system; questions are due 2026-07-21 and proposals close 2026-07-28.