Summary
Work includes 1 LS of mobilization; 15,674 LF of install #8 awg l-824c, 5000v, wire; 18,747 LF of install #6 awg bare copper counterpoise, including ground rods and terminations; 27,064 LF of install #8 awg thwn-2, 600v, wire; 6,766 LF of install #6 awg l-824c, ground wire; 18,396 LF of install 1-2" sch. 40 pvc conduit, direct earth buried; 351 LF of install 1-2" sch. 40 pvc conduit, concrete encased; 2 EA of install new l-827b junction box; 148 EA of remove existing runway edge light, complete; 32 EA of remove existing runway threshold light, complete; 1 EA of remove existing papi system from existing concrete foundations, complete; etc, see attached file.