Summary
The Project consists of: Removal, Disposal, and Replacement of clarifier equipment in three rectangular primary clarifiers, including but not limited to chains, flights, guides, drives, motors, weirs, scum troughs, handrails, and outdoor lights. Investigation and lining, repair, or replacement of primary sludge draw off lines. Mass grading, retaining wall, soil stabilization. Removal, disposal, and replacement of manual scum troughs in two chlorine contact tanks. All associated site utility work, grading, paving, electrical, systems integration to provide fully functional wastewater treatment plant infrastructure.