Cape Fear Public Utility Authority
Special DistrictNC
Posted
Oct 15, 2026
Nov 17, 2026
26-S0412 Asphalt Replacement RFP
Work include asphalt replacement.
Description: Work includes approx. 9,005 SY of 2-4" Mill Existing Pavement; 6,920 SY of 1"-2" Profile Mill Pavement; 2,195 SY of Concrete Base Repair; 2,710 TN of HMA 4E3; 700 TN of 2" HMA 13 A(modified); 16 EA of Adjust Manhole, Catch Basin or Inlet, Complete.
City · MI, US
From the first pre-RFP signals to the published RFP and its files.
Strategic plan
280 days before RFP
Warren's transportation asset management plan identifies asphalt and concrete roadway projects planned for 2026-2028 within a currently available budget of $13 million per year.
The Roadsoft network analysis of Warren's planned projects for the city major and city local networks from Warren's currently-available budget of $13 million per year does allow Warren to reach its pavement condition goals given the projects planned for the next three years. Planned Projects Warren has projects planned for the next three years (2026-2028).…
City of Warren Transportation Asset Management Plan 2025-2028
Strategic plan · Jan 14, 2026
Board meeting
196 days before RFP
The City’s 25–26 amended budget lists $1,358,563 for concrete/pavement repairs in fund 203.
REVENUE AND EXPENDITURE REPORT FOR CITY OF WARREN Balance As Of 02/28/2026 GL Number Description 25-26 Amended Budget Activity For 02/28/2026 Incr (Decr) YTD Balance 02/28/2026 Norm (Abnorm) Encumbrance 02/28/2026 Incr (Decr) Available Balance 02/28/2026 Norm (Abnorm) % Bdgt Used 203 3463 203-3463-80206 CONCRETE/PAVEMENT REPAIRS 1,358,563.00 0.00 826,397.90…
City Council Regular Meeting
Board meeting · Apr 8, 2026
Budget
112 days before RFP
Warren's adopted FY2027 Street Maintenance budget includes $1,650,000 for pavement repairs.
SPECIAL REVENUE FUND ACTUAL, ESTIMATED, REQUESTED AND APPROVED FY 2025 FY 2026 FY 2026 FY 2026 FY 2027 FY 2027 FY 2027 Actual Actual to Estimated Amended Budget MAJOR & LOCAL ROADS Departmental Recommended Adopted Year December 31 To June 30 December 31 STREET MAINTENANCE Request By Mayor By Council OPERATING COSTS Personnel Services: 116,196$ 56,909$…
Budget
112 days before RFP
The City Council's adopted FY2027 budget includes capital improvements for FY27 Dequindre, 12 Mile, Warner and Chicago projects and Section 12 paving.
SPECIAL REVENUE FUND ACTUAL, ESTIMATED, REQUESTED AND APPROVED FY 2025 FY 2026 FY 2026 FY 2026 FY 2027 FY 2027 FY 2027 Actual Actual to Estimated Amended Budget MICHIGAN TRANSPORTATION Departmental Recommended Adopted Year December 31 To June 30 December 31 OPERATING FUND - MAJOR STREETS Request By Mayor By Council DEBT SERVICE TRANSFER TO: 1,258,200$…
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (6 days left)
203-3463-80206 CONCRETE/PAVEMENT REPAIRS 1,358,563.00 0.00 796,293.56 0.00 562,269.44 58.61
City Council Regular Meeting
Board meeting · Jun 9, 2026
203-3463-80205 JOINT SEALING 180,000.00 0.00 76,750.00 0.00 103,250.00 42.64 203-3463-80206 CONCRETE/PAVEMENT REPAIRS 1,358,563.00 0.00 796,293.56 0.00 562,269.44 58.61 203-3463-94500 EQUIPMENT RENTAL 1,100,000.00 153,247.08 880,539.04 0.00 219,460.96 80.05 203-3463-96901 SUPERVISORY WAGES/FRINGES 238,757.00 0.00 0.00 0.00 238,757.00 0.00
Warren City Council Regular Meeting
Board meeting · Jul 28, 2026
City of Warren FY2027 Budget
Budget · Jul 1, 2026
132,159 378,545 2,078,563 2,078,563 Pavement repairs 1,650,000 1,650,000 1,650,000
City Council Regular Meeting
Board meeting · Apr 28, 2026
City of Warren FY2027 Budget
Budget · Jul 1, 2026
1,866,873$ 3,067,464$ 17,124,875$ 17,124,875$ Capital Improvements 6,416,000$ 6,416,000$ 6,416,000$ FY25 Projects: Sherwood (8 Mile to Toepfer), Chicago (Van Dyke to 13 Mile) and 13 Mile (Chicago to Campbell) & Common (Dequindre to Warner - South Side) FY26 Projects: Sherwood (Toepfer to 9 Mile), Hayes (Martin to Rudland), Martin (Ryan to David Givens), &…
City Council Regular Meeting
Board meeting · May 12, 2026
Decision makers connected to this RFP from City of Warren.
Adjacent opportunities open for bidding right now.
Cape Fear Public Utility Authority
Special DistrictNC
Posted
Oct 15, 2026
Nov 17, 2026
Work include asphalt replacement.
Wayne County Airport Authority
Special DistrictMI
Posted
Oct 20, 2026
Nov 10, 2026
The Wayne County Airport Authority is soliciting bids for the purchase of hot mix asphalt. The contract will run for one year. The posted description does not provide further details about specifications or quantities.
CityWY
Posted
Oct 27, 2026
Nov 19, 2026
Schedule A of the project includes the crushing, screening, moving, sorting, and processing of asphalt debris collected at the city of green river. Schedule B of the project includes the crushing, screening, moving, sorting, and processing of portland cement concrete debris collected at the city of green river. Schedule c represents the cost reduction, if any, if both schedules are awarded to the same contractor. Specifications for the desired finished products for each schedule are included in the project manual.
Special DistrictTX
Posted
Oct 6, 2026
Nov 3, 2026
Work includes removal of existing membrane roof (approx. 23,000 SF) and installation of new membrane roof (min. 60 mil thickness). Existing steel decking to remain. Removal of existing metal roof (approx. 2,000 SF) and installation of new standing seam metal roof. Removal of existing purlins and installation of new purlins. Removal of existing gutters and downspouts and installation of new gutters and downspouts.