Summary
Work inlcudes consists of the addition of 2,660 SF on the north side of the existing building and includes offices, classroom, and conference room. The construction will consist of wood trusses, wood framing, HVAC system, lighting, windows, doors, siding, and roof finished will match the existing building. The addition consists of wood construction, concrete footings, partial concrete slab and wood joist floor due to the grade change on the site, HVAC system, electrical, and lighting. The interior and exterior finishes will match the existing building. Site work includes demolition of the existing water storage tank, grading, installation of new water storage tank, new fire hydrant, gravel path from existing site to across