Summary
Requires specialized engineering services / maintenance /
system upgrades / parts replacement -( e.g., water filtration system maintenance) for the existing facility infrastructure system. The intended use is to ensure continuous, uninterrupted laboratory operations and maintain standard compliance. Heated and Chilled Seawater System Upgrades (all parts and equipment are brand name or equivalent): The Contractor shall isolate and lockout/tag out all utilities to ensure a safe working environment. The Contractor shall install Alfa Laval T6-PFG with EPDMP heat exchanger for sizing requirement upgrades. The Contractor shall Install Isolation Ball Valves, Temperature Control Pneumatic valve, Temperature Transmitter, Temperature and Pressure Indicators all mounted on epoxy-coated carbon steel skid. See attached file.