Summary
The project includes the following work: re-alignment of existing roadway, 16,319 SY of cold milling, 458 CY of street excavation, 409 CY of unclassified excavation, 1,734 SY of asphalt removal, removal and reconstruction of sidewalks, ADA upgrades, removal and reconstruction of curb and gutter, asphalt paving, signing upgrades, and pavement marking upgrades. construction of approx. 0.41 mi of walking path along heritage road, crow agency, MT. This portion of the project includes construction of the asphat walking path, removal and replacement of approach culverts, signing upgrades, and new pavement markings.